SMED on the shop floor: how to cut machine changeover from 90 to 40 minutes without investment
Lean · 5 min read · 24.09.2026

A changeover on a press takes 90 minutes. Of that, 12 minutes are spent looking for a wrench. 20 minutes waiting for the crane. Another 10 waiting for the first-article inspector. None of it shows up in the monthly report — just a few thousand fewer parts, written off to weak demand.
Do the math for one machine. Two changeovers a day, 20 working days, 90 minutes each. 60 hours of downtime a month. Seven and a half shifts you've already paid for — labor, energy, and depreciation. At a machine-hour rate of €40, that's €2,400 a month — on a single machine. And the pressure keeps growing: customers want smaller batches and more frequent deliveries, so the number of changeovers rises faster than capacity. In Foreast's projects, we see that management only realizes this once promised delivery dates start slipping.
The solution is called SMED — Single Minute Exchange of Die, changeovers in single-digit minutes. The method has half a century behind it and needs neither a new machine nor software. It needs a phone with a camera, a spreadsheet, and discipline. It works because most changeover time isn't work — it's waiting, walking, and searching. And that can be eliminated almost for free. When companies are postponing investments, this is the strongest argument there is for management: capacity you don't have to buy.
A hidden cost isn't the one you can't see. It's the one you've gotten used to considering normal.
Film it first, improve it second
Without a recording, no one remembers what they actually did during a changeover. Memory drops the waiting and shortens the walking. Everyone remembers their work, not their standing around. So take a phone, prop it against a stand, and film one ordinary changeover — not the worst one, not the best one, the kind that happens every week. Then go through the video with the foreman and the operator, step by step. Comparing the times together yields more than any instruction from the office.
Assign each step to one of two groups. Internal steps run while the machine is stopped: removing the fixture, mounting the new one, adjustments, trial parts. External steps the plant can handle without stopping the machine: bringing tools, preparing material, looking for documentation, notifying the inspector. The table has four columns — step, duration, internal or external, who does it — and the foreman can fill it in within one morning. In these analyses, we keep seeing the same numbers: only 30 to 40 percent of the time goes to work that actually moves the fixture. The rest is walking around the shop floor, searching, waiting for the crane, and repeated adjusting that never needed to happen.

Externalize everything you can
Every external step that today runs while the machine is stopped is a minute lost for free. The goal of the first wave: once the machine stops, the foreman must not take a single step that could have been done earlier. Everything must be finished before shutdown. Tools and gauges on a cart at the machine, not in a rack. Material positioned and checked, program ready. BOM, drawing, and setup parameters on the table. Quality inspector booked for a specific first-article time.
Put preparation in the hands of a named person, not "whoever happens to be free." Otherwise the checklist becomes just another piece of paper on the wall. Externalizing the external steps alone brings a 90-minute changeover down to 65–70 minutes. Without a single euro into the machine. It's the cheapest improvement we know in manufacturing — and most companies don't do it, because nobody is accountable for preparation.
Simplify, standardize, parallelize
The second wave attacks the internal steps — those that can only be done while the machine is down. Three changes have the fastest payback, and the shop can handle all three with its own resources.
First: a one-page changeover standard. Photos, sequence of steps, target times, responsibilities, a laminated sheet at the machine. With it, a new hire can perform a changeover without asking questions.
Second: a two-person crew on large machines. One removes and mounts, the other hands over parts, cleans, and prepares the next step. Parallel work recovers 15 to 20 percent of the time. Third: standardized clamping components. Uniform clamping heights, one wrench size for the whole machine, clamping assemblies pre-staged off the machine. Leave quick-release clamping solutions for later — for now it's enough to eliminate ten different hex key sizes.
Watch the end of the changeover. Adjusting and approving the first article is often the largest internal item, because the inspector shows up only when someone calls — and the call goes out only once the machine is set up. An agreed first-article time turns pressure into a planned event.
Add it up. Externalizing: minus 20 minutes. Parallel work: minus 10. The standard and an agreed first article: another 15 to 20. From 90 minutes, you realistically get 40. A machine with 40 changeovers a month thus recovers over 33 hours — four full shifts of capacity you've already paid for.
Key takeaways
- Film one ordinary changeover on your phone and split the steps into internal and external — the foreman can get it done in one morning.
- Move everything that can be prepared while the machine is running to before the stop: tools, material, programs, an agreed first-article time.
- Give large machines a two-person crew and standardize the clamping components — one wrench size, uniform clamping heights.
- Measure changeover time every week and post it at the machine. What gets measured goes down.
The goal for the first 30 days: one machine — the one with the most changeovers — one standard, and a measured time every week. Nothing more. Expansion to other machines will follow on its own once the foremen see the numbers. And when investments in new machines are being postponed indefinitely, you have an argument for management that needs no presentation: capacity you don't have to buy, because the shop floor already has it. That's exactly the spirit in which we build our cost reduction projects — first the minutes that are slipping away, then the millions you'd have to invest.
Tool changeover from 95 to 60 minutes: how an automotive stamping plant handled smaller batches
Standardized Work: How to Capture the Best Worker's Method for the Entire Shift
Value Stream Mapping: One Morning on the Shop Floor That Shows You Where Time Is Lost