18-Day Lead Time with 2 Days of Processing: How a Furniture Manufacturer Introduced WIP Limits
Lean · 3 min read · 30.09.2026

Client
A mid-sized furniture manufacturer, 240 employees, production running in two shifts. The process technology consists of panel cutting, surface finishing, assembly, packaging, and shipping; a substantial share of output is custom furniture for commercial interiors. Most orders were one-off or small-batch. The company is presented anonymously — this is a composite case study drawn from multiple projects we have delivered in this segment.
The project was initiated by the operations director. He made the decision only once late deliveries had put a key business partner at risk and management had rejected the solution of renting yet another warehouse.

Challenge
Every operation ran at its own pace. As a result, buffer stockpiles built up between cutting, surface finishing, and packaging — parts sat in them for days, in the worst cases up to three weeks. The stock took over corridors and free floor space around the lines. Average lead time from cutting to shipping was 18 days, even though total pure processing took less than two days. The rest was waiting and moving.
Orders got lost between operations. Asked where a specific order stood, no one could answer without walking the halls; 15% of deliveries were late. Sales reps were fighting fire after fire, while the company was paying for something no one had planned: tied-up capital, occupied floor space, and hundreds of hours of material handling a year.
Approach
- Mapping the material flow. Our consultants, together with the production staff, walked the entire flow from cutting to shipping and measured waiting times at every interface — in both shifts, right on the shop floor. The output was a value stream map breaking down processing time versus waiting time. It already made clear where the problem sat: not in machine capacity, but in managing the queues between operations.
- WIP limits at the interfaces. Instead of unrestricted buffering, we introduced fixed pallet limits between cutting, surface finishing, and packaging. Once a limit was reached, the upstream stage did not start a new order until the queue cleared. This slowed the flow down exactly where it was overfed. The foremen were nervous during the first weeks; the queues stabilized sooner than even our team expected.
- Sequencing by shipping dates. We changed both batch sizes and the order of work: parts entered surface finishing based on actual delivery dates, not on how easy the machines were to change over. Orders were split into smaller batches and traveled through the flow as complete sets, so assembly received full kits instead of half-sets. The sequence was approved by the planning meeting once a day.
- Visual management of movement. Every pallet was given a clear location, status, and owner. Short meetings at the line, twice per shift, dealt with whatever was blocking the flow. Hunting for orders through the corridors came to an end.
- Embedding the measurement. Daily lead time and the on-time delivery rate were added to a single board. The foremen gradually took ownership of the limits and the rules; whenever lead time exceeded 10 days, the production meeting addressed the root cause that same day.
Results
The changes took approximately five months; the first improvement in waiting was visible after six weeks.
- Work in progress reduced by 45% — approximately 600 m² of floor space was freed up and now serves assembly.
- Lead time cut from 18 to 9 days from cutting to shipping.
- On-time delivery improved from 85% to 96%.
What did not happen along the way: we needed no investment in a new line, a racking system, or a third shift. The capacity the company had been looking for was in the buffer stockpiles all along. A year after the project, the limits are holding — the foremen check them on a regular walk and lead time is still measured daily to this day.
Are you dealing with similar buffer stockpiles in your production? See how we work on cost reduction.
Tool changeover from 95 to 60 minutes: how an automotive stamping plant handled smaller batches
Standardized Work: How to Capture the Best Worker's Method for the Entire Shift
Value Stream Mapping: One Morning on the Shop Floor That Shows You Where Time Is Lost