On-Time Delivery at 71%: How a Switchgear Manufacturer Moved from Paper to a Digital Work Order
Digitalisation · 3 min read · 16.09.2026

Client
An electrical engineering company with 85 employees, custom switchgear manufacturing in a single shift. Almost every order was different — from configuration to shipping documentation. Deadlines were hard: other suppliers installed the switchgear on construction sites, so one delayed delivery pushed the entire construction schedule. The operations director kicked off the project after three consecutive complaints, all with the same root cause: incorrect cable configuration.
The company is presented anonymously. This is a composite case study drawn from several of our projects in the electrical segment; the events and figures fall within the normal range of these projects and do not disclose any identifiable detail of a specific customer.

Challenge
Production ran on paper work orders. Workers confirmed each operation — cable cutting, assembly, wiring, testing — with a signature, and the paper travelled around the shop floor. Planning only learned the status during walk-arounds, so sales promised deadlines based on estimates, not data. Capacity was maxed out, delays were handled by rescheduling, and there were no buffers.
The consequences were measurable. On-time delivery (OTD) had long been stuck at 71%. Material and test reports for shipping took an average of two days to track down — a finished switchgear waited for a missing piece of paper. The end-of-line inspector saw signatures, not the actual configuration, so wiring errors travelled all the way to the customer. Every complaint meant a service call and the risk of losing the next order.
Approach
- Order flow mapping. Our consultants walked twenty orders through with the foremen, from receipt to shipping, recording where paper waited and where information got lost. Most delays arose not from the work itself but from the handoffs between workshops.
- Digital work order pilot. In one workshop, we replaced paper with a digital work order on a tablet; the worker confirms an operation with a tap and a serial-number scan. No expensive MES system was needed — the shift mastered it without a week of training.
- Checks built right into the work order. Before confirming an operation, the electrician goes through a checklist based on the wiring diagram: number of conductors, terminal markings. A configuration error is caught at the workstation where it originated — not at the customer's.
- Traceability and automatic documentation. Every scan logged the time and operation against the serial number. Test reports and serial number lists for shipping are compiled automatically, and searching through papers has been replaced by a real-time overview of order status.
- Rollout and data-driven management. After two months, we deployed digital work orders across all workshops. Production planning received a board with the status of every order, and the morning meeting sets priorities based on data — the foreman sees a stuck order before it even reaches him.
Results
The rollout was phased — pilot first, then the entire production operation. The first measurable changes came within three months, stable results within nine.
- On-time delivery rose from 71% to 94% within nine months of the pilot.
- Preparing shipping documentation was shortened by 70% — from two days of searching to a single morning.
- Cable configuration errors dropped by half; the checklist catches them right at the workstation.
The team's concerns never materialized — no expensive information system, no second shift, no layoffs. The electricians mastered the digital work order within days, because it replaces the paper they filled out anyway. They use the data trail daily: when a complaint comes in, the company can tell within a minute who did which operation and when, and sales quotes deadlines verified in the system, not estimates.
Days spent searching for documentation and last-minute shipping are costs accounting will never show — but the customer notices them in the delivery dates. If you are looking for similar hidden reserves, take a look at our approach to cost reduction.
Your first cobot on the shop floor: how to choose the operation and calculate the payback
From Estimates to 49% OEE: How an Automotive Supplier Moved to Online Machine Monitoring
Job tracking vs. production intelligence: what to implement on the shop floor first