From Estimates to 49% OEE: How an Automotive Supplier Moved to Online Machine Monitoring

Digitalisation · 3 min read · 28.10.2026

Client

The client is an automotive industry supplier with a production program focused on precision machining. Around 300 employees, nearly forty production machines, three-shift operation. We present the company anonymously — this is a composite study of several projects we have delivered in this segment. Names, locations and identifiable details have been omitted, and we keep the numbers within conservative ranges.

The project was initiated by the operations director. Repeated delivery delays were addressed at shift handovers with speculation about what had actually happened on the shop floor. He wanted real data before a customer requested it during an audit. Guessing is not managing.

Challenge

Production reports were transcribed manually — from paper logbooks into a spreadsheet, from the spreadsheet into a report. No one knew the actual machine utilization. Estimates ranged from 50 to 60 percent, and without a real number it was impossible to decide whether to accept another order, or where to look for reserves.

The bigger problem was response speed. When a machine stopped at night, it was only discovered at the morning shift handover. The night shift ran idle, and several times a month the company lost eight hours of capacity without a single report. Production was, in effect, managed with a twelve-hour delay.

Approach

  1. Measurement without opinions. For two weeks we collected data directly from the machines — from the control signals the machines already had, but that no one was using. Reality was worse than all the estimates: 49 percent OEE. This number became the shared baseline of the project.
  2. Cause catalog and response rules. With foremen and operators we defined what counts as downtime and compiled a catalog of reasons — from tool changes to waiting for material. Each reason has a responsible person and a response time. Without this step, monitoring would only measure the chaos more accurately.
  3. Online monitoring and andon. We deployed status visualization on the shop floor and instant notifications for foremen and shift leaders. Every downtime longer than two minutes is automatically logged with a reason. The response comes during the shift, not the next morning.
  4. Attack on the three biggest causes. The catalog showed that waiting for material, setup, and waiting for inspection together accounted for more than half of downtime. For each of them we introduced a simple standard: pre-staged tools, material prepared before the start of the shift, inspection directly at the machine. Nothing revolutionary — but it was followed every shift.
  5. Data-driven shift handover. The handover changed into a ten-minute review of yesterday's numbers, not memories. Once a week an OEE review by cause takes place, and the three most frequent downtime reasons receive corrective action.

Results

The changes showed progressively; the full effect came after six months:

  • Machine park OEE increased by 14 percentage points — from the measured 49 to 63 percent.
  • Average downtime duration fell by a third, from 45 to 30 minutes.
  • Unreported full-shift downtimes: from 3–4 cases per month to zero.

We didn't buy new machines or invest in automation — the capacity was found in the existing machine park because it stopped leaking away. No one was laid off; people got data instead of a logbook. Today andon is part of shop floor discipline: when the red light is on, someone responds within minutes. The cause catalog and weekly reviews are run by the foremen themselves; our consultants do not interfere with the daily routine.

In projects in this segment we keep seeing the same pattern: without data, a double-digit number of OEE percentage points is lost to delayed response and poor downtime planning alone. We apply the same approach — measure, define, visualize, manage — in cost reduction projects as well. To see how such a project runs from the first analysis to completed corrective actions, take a look at cost reduction at Foreast.